Perbaikan Tanggul Kali Ciliwung di Kenari Dikebut

SDA Accelerates Ciliwung River Embankment Elevation Work in Kenari

Senen Sub-district SDA Unit accelerates Ciliwung River embankment elevation work along Jalan Kramat IV - VI, Kenari Urban Village, Senen Sub-district, Central Jakarta.

We estimate it to finish in the next two weeks

According to Senen Sub-district SDA Unit Head, M. Rohman, his side began elevating the embankment since mid of July. From total length of 418 meters, currently his side has completed 80 percent or about 335 meters.

"We estimate it to finish in the next two weeks," he stated, Friday (11/6).

Wave Break Embankment on Kelapa Island Beautified

According to him, this embankment was built with width of 0.85 meters and average height about 60 centimeters from the road surface.

After this work is completed, he continued, his side will continue to repair Ciliwung River embankment that crosses Kenari Urban Village as requested by the local residents.

"We will continue to repair other parts of embankment after we finished elevating and painting Ciliwung River embankment along Jalan Kramat IV and VI," he conveyed.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2386 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1096 personAldi Geri Lumban Tobing
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye994 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye860 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye755 personBudhi Firmansyah Surapati